Rehabilitation of the Three Kindergarten Classrooms of EPP Fanara - 2016

Lutte contre la pauvreté, Nos activités, Rehabilitation Des Salles De Classe

The project to rehabilitate the three kindergarten classrooms of EPP Fanara took place between February 21 and May 7, 2016 in the Atsinanana region. The main goal was to provide access to education for about 75 students who had been without it. The project also contributed to the annual "Aid for the schooling of disadvantaged children in rural areas" program, aimed at supporting the excellence of EPP Fanara.

The project was carried out with the complete rehabilitation of the three kindergarten classrooms. The work included repairing the roof, the flooring, and the exterior and partition walls, which had been devastated by a cyclone several years earlier. The total cost of the project amounted to 3,225,600 Ariary, or 921.60 € for the period in question. Thanks to this project, EPP Fanara was able to guarantee access to education for the children.

Photo gallery

accès à la scolarité aide à la scolarisation Ariary coût cyclone déplacement enfants enfants défavorisés environs EPP FANARA excellence maternelle programme annuel réhabilitation résultats salles de classe soutien transport zone rurale